Key technical specifications RXQ16BYM
-
Model: RXQ16BYM
-
System type: VRV A – Cooling only
-
Refrigerant: R410a refrigerant – Environmentally friendly, high efficiency
-
Cooling capacity: 154,000 Btu/h (~ 45kW)
-
Power consumption: 12.6kW
-
Dimensions (Height x Width x Depth): 1,660 x 1,240 x 765 mm
-
Weight: 270 kg
VRV A Cooling-Only Outdoor Unit, R410a Refrigerant – Model RXQ16BYM | Capacity 154,000Btu/h
RXQ16BYM product introduction
VRV A cooling-only outdoor unit – Model: RXQ16BYM is a premium central air conditioning solution from a leading Japanese brand. With a cooling capacity of up to 154,000 Btu/h (equivalent to 45kW), the product is suitable for large commercial projects such as office buildings, hotels, shopping centres…
RXQ16BYM key technical specifications
-
Model: RXQ16BYM
-
System type: VRV A – Cooling only
-
Refrigerant: R410a refrigerant – Environmentally friendly, high efficiency
-
Cooling capacity: 154,000 Btu/h (~ 45kW)
-
Power consumption: 12.6kW
-
Dimensions (Height x Width x Depth): 1,660 x 1,240 x 765 mm
-
Weight: 270 kg
RXQ16BYM outstanding advantages
-
Energy savings with advanced inverter technology, helping reduce operating costs.
-
Stable operation in all weather conditions, ensuring effective cooling for large spaces.
-
Easy installation and maintenance, with a compact design that optimises installation space.
-
Environmentally friendly thanks to the use of R410a refrigerant, which does not deplete the ozone layer.
RXQ16BYM practical applications
The VRV A outdoor unit model RXQ16BYM is suitable for use in:
-
Company offices, administrative headquarters
-
Hotels, restaurants
-
Shopping centres, showrooms
-
Hospitals, schools
Why choose Model RXQ16BYM?
✅ Powerful cooling performance
✅ Quiet operation, high durability
✅ Outstanding energy savings
✅ Reputable brand, official warranty
Contact us now to receive the best quotation and advice on a VRV central air conditioning solution suited to your needs!
🔧 TECHNICAL GUIDE TO INSTALLING THE VRV A OUTDOOR UNIT – MODEL RXQ16BYM
1. 🧰 Preparation before installing RXQ16BYM
a. Required tools and equipment:
-
Drill, welding machine, bolt-fastening tools
-
Pressure gauge, thermometer, clamp meter
-
Vacuum gauge (vacuum gauge)
-
Dedicated vacuum pump
-
R410a refrigerant for checking and topping up if necessary
b. Check the installation site:
-
The base must be level and solid, not sloped, with a load-bearing capacity greater than 300kg
-
A well-ventilated location, protected from direct sunlight and heavy wind-driven rain
-
Minimum service clearances:
-
Front: ≥ 1,000mm
-
Rear: ≥ 300mm
-
Both sides: ≥ 300mm
-
Above: ≥ 1,000mm
-
2. 📐 Mechanical installation of RXQ16BYM
a. Outdoor unit dimensions:
1,660 x 1,240 x 765 mm, weight 270kg
b. Positioning and securing the base:
-
Use M10 or M12 bolts to secure the unit feet to the concrete plinth
-
The plinth must have a minimum height of 150mm above ground level to prevent flooding
c. Ensure vibration reduction:
-
Use anti-vibration rubber mounts or vibration isolation pads under the unit feet
3. 🔌 RXQ16BYM electrical installation
a. Power supply:
-
3-phase power 380V - 50Hz, supplied separately to each outdoor unit
-
Electrical cables must meet standards for heat resistance and current-carrying capacity above 20A
b. Wiring:
-
Connect in the correct phase sequence L1-L2-L3 and earth according to the wiring diagram supplied with the unit
-
Check the fan rotation direction after powering on for the first time (if it rotates in reverse, swap 2 phase wires)
c. Safety precautions:
-
Always disconnect the power before carrying out any work
-
Install a CB and surge protection in accordance with industrial electrical regulations
4. 🔗 RXQ16BYM refrigerant piping installation
a. Refrigerant piping:
-
Use copper pipes of the standard wall thickness for R410a, fully insulated
-
Ensure the piping has no kinks, dents or leaks
-
Maximum piping distance according to the manufacturer's recommendations (for example: 165m in length, 50m in elevation difference)
b. Vacuum evacuation:
-
Evacuate the entire system for at least 30 minutes until the pressure reaches below -756mmHg
-
Check for tightness using a pressure gauge and test for leaks using soapy water
c. Additional refrigerant charging (if required):
-
Calculate the refrigerant charge required based on the actual pipe length (for example: add x g of refrigerant/1m of piping beyond the standard length)
d. Condensate piping:
-
Ensure a slope ≥ 1%
-
Install an additional water trap and strainer to prevent blockages
5. ⚙️ RXQ16BYM startup and test operation
-
Perform a final check of all electrical, refrigerant and drainage connections
-
Switch on the power, start the system via the central controller
-
Monitor:
-
Refrigerant suction and discharge pressures
-
Outdoor unit temperature, noise, vibration
-
Compressor load current
-
-
Record operating parameters to compare with the manufacturer's standard parameters
6. 🛠 Post-installation maintenance for RXQ16BYM
-
Clean the filters regularly every 3 months
-
Check refrigerant and operating pressure every 6 months
-
Service the entire system at least 1 time/year
Do you need me to convert this article into a PDF file or print an installation technical checklist form for convenient use on site?
Technical specifications
Customer reviews
Share your review of the product
Ratings and reviewsRelated Products
RXQ18BYM
RXQ14BYM
RXQ12BYM
RXQ10BYM
RXQ8BYM
Daikin VRV A Max 60HP RXQ60AMYMW Outdoor Unit - HRT
DAIKIN VRV A Max 58HP RXQ58AMYMW Outdoor Unit - HRT
DAIKIN VRV A Max 56HP RXQ56AMYMW Outdoor Unit - HRT
Sender information
- There are no products in the cart